Hi

Trying to use BCS with Funded Program account assignment element active. The set up is 1:1 of WBS Element to Funded Program by creating equalent number of funded programs in FM. Budget will be entered at Project level Funded program.

We would like system to check budget availability check in BCS at Project level. I believe it can be possible to create assignment source field as WBS Element number to derive target field as Funded program by removing last 4 digits to arrive at Project number.

Is this set up will work? If yes is it possible to run reports at WBS Element level? Is there any function similar to Commitment Item hierarchy where all Funded programs within a project can be grouped? Please help.

Thanks