Dear All,

Please I have a problem , When I'm  working  on any document of material all documents are locked of the same material at the same time for example If i receipt a new goods from the vendor when the Finance user go to make an invoice of it on specific purchase order all inspection lots of the same material at the same time are locked by Finance user , so any one can help me to avoid Disrupts of  the system work flow .

Thanks,

Accepted Solutions (0)

Answers (1)

Answers (1)

tomas_talpa
Active Contributor
0 Kudos

Hi amr,

see SPRO: Materials Management -> General Settings for Materials Management -> Set material block for goods movements & Set Up Material Block for Invoice Verification. Here you can specify when / how late the material will be locked.

Kind Regards

TomT

former_member294408
Participant
0 Kudos

Dear TomT,

Thank you it is work correctly thanks very match

tomas_talpa
Active Contributor
0 Kudos

I'm happy to hear that, Amr. It is time to mark your question as 'answered', so future viewier will know the status.

Kind Regards