cancel
Showing results for 
Search instead for 
Did you mean: 

Alternative Valuation run for Calculating Correct Inventory Balance for the Past Period

Former Member
0 Kudos

Hi Experts,

Let's say 6 months already past since the cutover of SAP production system.  We have activated material ledger.

In the past, we have encountered several issues for allocating the variance to ending inventory and COGS.  For several months of improvement activities,

We have fixed some issue, change configuration, and corrected the wrong master data.  HOWEVER, material ledger post BS accounts which affect the next periods balance for long period of time.  Also PL must have been wrong due to this wrong ML calculation. 

We are thinking to run Alternative valuation so that we can calculate the "should have been" correct figure for the past 6 month periods.

So, I need to know to run this guy to fulfill this requirement.  Please give me the step by step method to run alternative valuation like below.

IMG> XXX>XX active something

T-code : XXX to valuate alternative figure

Detailed explanation for selection paramter would be highly appreciated if possible.

We DO NOT need PERFECT figure, but need a "may be" correct figure generated from reliable source like SAP standard functionality.

Thank you in advance for your kindly reply.  Must run it this transaction.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I asked CO Expert from SAP (Max attention).

You can run Alternative valuation run easily using t-code CKMLCPAVR.

CKMLCPARV works pretty much same with normal CKMLCP except you can specify

From period and various parameter setting for actual cost calculation in CKMLCPAVR.

Thanks