Hi gurus,
My client has the current process flow for release of DP forecast in manugistics to ECC
On a weekly basis, the DP forecast is sent to a flat file and stored for 8 weeks in future - All locations are warehouses as demand is at the warehouses(There are 18 unique warehouses)
A custom program will pick up the forecast from flat file and maps the Product X Warehouse combination to Product X Central distribution center - (There is a single central distribution center only. So all the 18 warehouses are mapped to single distribution center)
In MD61 the PIR are seen for product at the central distribution center(#031).
If the same scenario has to be configured in DP, what are the steps for configuration and what is the role of the ABAP person? Is there any user exit for this? Is there an alternate solution?
Any quick responses are appreciated!
Sunnyji