on 10-15-2012 1:20 PM
Hi All,
i plan cost for activites with costcenter 4290 and activity type , i confirm the activities so actual cost is posted to activites. My strucutre consists of 2 level all the cost plan is done at 2nd level and confirmation is also done for the activites of 2nd level wbs elements. the actual cost is at level 1. for settlement i maintain rule for level 1 wbs element in order to settle to cost center 4290. when i execute settleement ie cj88 it is executed without any errors but i am not able to see any details. i am not able to close the project as the cost is still at activity level. could anybody guide me to close the project.
regards,
abhinay.
Hi Tushar,
the link doesn't explain much.As far as know i define settlement profile with required receivers, for settlement strategy for wbs structure ( as my project limit to wbs) the settlement rule strategy settings contian AAc Ass row in which it has two specific options regarding cost center could you explain the differnece betw them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhinay,
Settlement rules for WBS elements are determined by a range of different strategies which are defined in Customizing. In case of Cost projects, system can derive settlement rule for WBS elements from the cost center responsible, or the requesting cost center.In the settlement rule strategy, one can specify the sequence in which the settlement rule is to be determined.
For more details , refer sap help at below link
http://help.sap.com/saphelp_470/helpdata/en/23/52298e099b11d2add30000e8a6353a/content.htm
Regards
Tushar
Hi Tushar,
Thanks for your link but i am getting confuse while reading the process, the thing which i understand upto know is that in order to transfer actual cost from project to any cost objects we use settlement proces . for that we maintain settlement rule for wbs elements(ie senders).2) in settlement profile we maintain the proces fro settlement and receivers. 3) in trans code CJ 88 we execute setlement..
but i am not sure of maintianing setlement rule, generate settlement rule directly and also the whole sequence could you please provide any data which will be very helpful for me.
regards,
abhinay.
Hi Tushar,
Thanks for your link but i am getting confuse while reading the process, the thing which i understand upto know is that in order to transfer actual cost from project to any cost objects we use settlement proces . for that we maintain settlement rule for wbs elements(ie senders).2) in settlement profile we maintain the proces fro settlement and receivers. 3) in trans code CJ 88 we execute setlement..
but i am not sure of maintianing setlement rule, generate settlement rule directly and also the whole sequence could you please provide any data which will be very helpful for me.
regards,
abhinay.
Hi Abhinay,
For your reference, please look at below mentioned link
http://help.sap.com/saphelp_470/helpdata/en/d4/03e247f5f211d1adc50000e8a6353a/content.htm
I would suggest you to do some search on help sap before posting any querry...
Settlement process has been discussed number of times on scn and if you search it, you will find lot of threads which can clarify your doubts.
Regards
Tushar
Hi Tushar,
the link doesn't explain much.As far as know i define settlement profile with required receivers, for settlement strategy for wbs structure ( as my project limit to wbs) the settlement rule strategy settings contian AAc Ass row in which it has two specific options regarding cost center could you explain the differnece betw them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhi,
Make sure if any liability is on project then project can not closed properly and originate various errors until all wouldn't be cleared.
Go through below link already discussed in forum:
http://scn.sap.com/thread/1451395
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Abhinay,
Please check whether you maintained settlement profile for network, so that all cost of network would be settle on related WBS. Than Settlement rule for WBS will be receiver as Costcenter so all he cost should be transferred to actual receiver that is Cost Center.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ensure that, you are settling your NWA cost to your level 2 WBSE, which is rolling up to level 1 WBSE.
As Tushar said, check CJI3 and you'll come to know which cost/commitment is still pending at what level. This should help you to resolve your issue.
Good luck
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Your actual costs are sitting at Level 2 WBS element and maintained the settlement rule at Level 1 WBS.
Where is your NWA costs are settling in this case, hope it is from NWA to WBS level 2.
If hierarchy structure maintained properly the actual costs at aggregate level 1 would be settled to CTR properly. I guess can you post screen shot how your WBS arrangement was done in PB.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhinay,
Check CJI3 report and see if the total of the cost is ZERO. If the cost is not ZERO, then it means settlement has not executed completely. In such case, through CJI3 , you can see which of the cost is not settled.
Check CJI5 report and see if there are any open commitments (PR,PO) for specific activity. If yes, then you need to close those PO by setting Deliv.compl. checkbox.
Please follow link mentioned below which can be helpful.
http://scn.sap.com/people/sourabh.saxena/blog/2008/11/21/analysis-of-ps-project-closing-errors
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Tushar,
i define settlement profile with costcentr as optional. in Project structure i maintain settlement rule for activites each activity settlle the cost to resp wbs element. i maintain settlement rule for each wbs element with cost center as receiver. but i am not able to settle the cost to cost center.