Dear Gurus,
I am currently facing an issue while trying to use R1 time phased planning MRP type.
Indeed I am not able to understand the results obtained after making an MRP run.
Material configuration, calendar and PIRs details are described within the attached file : Material_Config.jpg
MRP results are given within the following screenshot : MRP_Result.jpg
Considering 7 days for delivery time and a planning calendar defined every Wednesday, generated Purchased Request should cover PIRs of the 15th of Oct. and the 22th of Oct.as described in the following image : Expected_Results.jpg
My questions are, considering the data set used :
- Why generated Purchased Request is covering Independent Requirement of the 29th of October and the 05th of November?
- Why 22 (6+6+6+4) pieces are included into this PR and not 34 (6+6+6+16) pieces as shown in the request chaine (see Expected_Resutls.jpg)?
Thanks in advance for your answers.
Lionel