Oct 14, 2012 at 06:39 PM

R1 Time Phased Planning Results Misunderstanding

1027 Views

Dear Gurus,

I am currently facing an issue while trying to use R1 time phased planning MRP type.

Indeed I am not able to understand the results obtained after making an MRP run.

Material configuration, calendar and PIRs details are described within the attached file : Material_Config.jpg

MRP results are given within the following screenshot : MRP_Result.jpg

Considering 7 days for delivery time and a planning calendar defined every Wednesday, generated Purchased Request should cover PIRs of the 15th of Oct. and the 22th of Oct.as described in the following image : Expected_Results.jpg

My questions are, considering the data set used :

- Why generated Purchased Request is covering Independent Requirement of the 29th of October and the 05th of November?

- Why 22 (6+6+6+4) pieces are included into this PR and not 34 (6+6+6+16) pieces as shown in the request chaine (see Expected_Resutls.jpg)?

Thanks in advance for your answers.

Lionel