MRP using KE11 Sales Plan

hussain_multhazim
Participant
0 Kudos

Hey SD experts

I want to use sales plan which is uploaded in KE11 to plan the production process. What is the process of using KE11 sales plan values for production planning ?? THanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

eduardo_hinojosa
Active Contributor
0 Kudos

Hi

You can use the SOP (Sales & Operations Planning). See the printfile for PP-SOP in this link http://help.sap.com/printdocu/core/print46c/en/data/pdf/ppsopdrp/ppsopdrp.pdf

You can populate SOP from COPA using the tcodes KEPA and OKEQ. Search them in the IMG node for COPA (or tcode ORKE) in planning.

I hope this helps you

Regards

Eduardo