on 10-09-2012 4:15 PM
Hi,
Project AUC asset not yet settled since 2010 onwards, now user wants to settle the AUC Project.
system not allowing to settle the project, how do we proceed to settle the project.
Error: First settle items from previous year in previous year 2011: 822234208/001
Acquisition value negative in area 01.
Regards,
Murali.
Hello Murali
The system only considers items from the current fiscal year,
I think you need the note 819197 here
I found that some customer limit standard transaction types for retirements,
Please take off any limitation. The settlement needs the standard
transaction types to be unlimited to perform the necessary retirement
simulation which is performed internally during the settlement process.
hope this help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murali,
It has been discussed in this forum.
Please search forum before posting a query. If you have any specific case then you are welcome to post in forum.
Options are-
1. Open previous period and settle the project from first period.
2. use kb21n to transfer cost from WBS to cost center and open previous period and run settlement. However it will settle with amount 0.
3. Convert message from error to warning (Not recommended).
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murali,
Can you please ask to your CO guy weather there is any functionality of special periods among 12 posting periods exists. if exists,you can post the same entry and the document will be posted in the last working day of the last period during the special period.
Secondly, if you are with the periodic(PER) settlement rule then you have to settle only in the that particular period. And, if settlement done to CO object then you need not to open the FI period.And, if it is to an asset or G/L then you need to.
I just found a SAP Note 819197,Please check it and let us know if it could work in your case.
Till then, let's wait for other experts suggestions on the same.
Regards
Ankur
Hi Ankur,
Thanks your suggestion,
1.We have Sepcial periods functionality, but this Project AUC asset credit value shows 2010 year onwards, this financial year already closed,client will not accept to open any periods.
2. Settlement Rule type AUC (PER), this is not possible now.
SAP Note 819197 this note cannot be implemented.
Regards,
Murali.
Hi Murali,
Please check if SAP note # 82514 can help you.
Symptom
When you settle an investment measure, (an order or WBS element with related Asset under Construction (AuC)), the following error messages appear:
AW 624: First settle items from previous year in previous year &1: 3
KD 625: Settle the balance from previous year in previous year first.
Regards
Tushar
Hi Murali,
Check below mentioned thread which is similar to your issue.
http://scn.sap.com/message/7741567
Also check note 425601 at below mentioned link
http://www.stechno.net/sap-notes.html?view=sapnote&id=425601
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.