Price per unit tab in KP26

Dear Experts,

While planning the activity cost in kP26, Price per unit showing 10 units instead of 1.

For Example:

It is showing Rs.100 for 10 units ( one unit cost is 100/10=10)

I need to see Rs.10 for 1 unit.

In kP26

Activity Type

(1)

Plan Activity

(2)

Distribution key

(3)

Capacity

(4)

Dis key

(5)

Unit

(6)

Plan Price

(Fixed)

(7)

Plan Price

(Variable)

(8)


Price Unit

(9)

Plan Price Indicator

(10)




5 Machine 1200 2
2 MIN 100
00010 1




Machine 1200 2
2 MIN 10
00001 1




I am expecting the result as per Row number 2. Please guide me how to get it.

Thanks

Jyoshna

Add comment
10|10000 characters needed characters exceeded

1 Answer

  • Posted on Oct 07, 2012 at 03:33 AM

    hi

    If u are calculating plan activity prices automatically through SAP, it automatically derives the price unit there is no manual intervention here. you can change manually as per your requirement once price calculation is executed as the price is already calculated

    but what my observation is based on activity unit maintained system will derive this price unit, try to change minutes to hours system will change the price calculation according to your requirement

    krishna

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear jyosh,

      Once you run the KSPI click on goto in the menu bar--> format--> price unit--> 1 then save the KSPI now system will save the per unt price after that check the results in KSBT report.

      Regards,

      ravi.