Profit center xxxx/700000 does not exist for 04.10.2012

Dear Experts,

I am an ABAP developer, my client was using our product in 4.7 and recently decided to migrate to ECC 6.0, Here in ECC 6.0 they have made document splitting mandatory, in our product we are posting into FI, the thing is while posting we are not giving any cost center or profit center and since those are not mandatory in 4.7 the product was working fine but when we moved to ECC 6.0, when i am doin posting the following error came Balancing field "Profit Center" in line item 001 not filled, so while debugging i forcfully added the profit center created for that company code, as the accounts against which i was doin posting was a balance sheet account, but when i do so i get the following errors.

Profit center XXXX/700000 does not exist for 04.10.2012

Profit center XXXX/700000 does not exist for 04.10.2012

Profit center 700000 not found in controlling area XXXX

Profit center XXXX/700000 does not exist for 04.10.2012

Profit center 700000 not found in controlling area XXXX

Profit center XXXX/700000 does not exist for 04.10.2012

I also checked for the validity of the profit center in KE53 and it has been kept as 01.04.2003 to 31.12.9999 and status is also active and also profit center has been assigned to the company code.

and the above said error is occuring when i pass it as parameter in the fllowing BAPI 'BAPI_ACC_GL_POSTING_CHECK'

Since i am not of FI background i am unaware of the demographics of functional side of SAP.

Please Help!!!!

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 17, 2012 at 04:37 AM

    Hi,

    The problem was solved i assigned default profit center in FAGL3KEH for the respective G/L codes as at present cliet was having only a single profit center for the company code.

    Thanks!!!!!1

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 04, 2012 at 06:12 AM

    hi

    Could you pls check the controlling area assignement..if its assigned correctly......

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 04, 2012 at 09:57 AM

    Dear Joy,

    Use T.code 0KE4 to update controlling area( Controlling area setting will update).

    I hope it will help you

    Regards

    RAHEEM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 24, 2019 at 10:34 AM

    Thanks a lot my Issue Resloved

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.