How To calculate Earned Value

0 Kudos

Hi Team,

Please tell me the process to calculate EV in SAP PS.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Neha,

In addition, you can also refer below pdf on Project progress showing how earned value is calculated.

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PSPRG/PSPRG.pdf

Regards

Tushar

former_member195427
Active Contributor
0 Kudos

Hi Neha,

            In addition to Sanjeev's reply I would suggest you to read and understand more about EV . There are many threads discussed already in the forum on EV. I am giving a few links here below:

http://scn.sap.com/thread/1598320

http://scn.sap.com/thread/1917873

http://scn.sap.com/thread/2080544

In addition also refer SAP Library, SAP help on the same.

Regards

Ankur

sanjeevc
Active Contributor
0 Kudos

HI,

You can do the following customizing steps... this will help you to configure as per your needs. This is not as per your need, as only you can understand what all the customizations you need to do........

  

1. Create Progress Version 101 with exclusive use 'Progress Analysis'. I have selected Plan & Actual check boxes.

2. Settings for Progress Version-

a) Plan version - '0'

b) EV basis - Cost plan (active project, annual values)

c) POC weighting - Cost plan (active project, annual values)

d) Planning type - Basic dates

e) Early / Late - earliest possible

f) Both reference boxes selected

3. SKFs (statistical key fig.)- I created three SKFs 10 (Non-Aggregated POC), 20 (Aggregated POC) and 30 (POC for RA) with unit of measure '%' and selected the Key value category 'Total values'.

4. I need to assign these SKFs to different value categories. I created three value category 10, 20 & 30 with selection 'SKF with total values' and unit of measure '%'. Then I assigned SKF 10 to VC 10, SKF 20 to VC 20, SKF 30 to VC 30

5. I assigned measurement method as default value:

a) WBS (Plan) - Cost Proportional

b) WBS (Actual) - Cost Proportional

c) Internal Activity (Plan) - Cost Proportional

d) Internal Activity (Actual) - Degree of Processing

c) Exernal activity(Plan) - Cost Proportional

d) Exernal Activity (Actual) - Degree of Processing

6. I made progress cost element '6511100' (Secondary cost element) with Cost element category as 61.

7. I maintain a value catagory 6511100 with Cost radio button selected.

And assigned the progress cost element to the value catagory. i.e Cost element 6511100 to value catagory 6511100.

8. I maintain the assignment of cost element group. ie. I assigned progress cost elemnt to cost element group with default radio button selected. In the cost element group, I have selected certain cost elements which we regularly used (cost elements for project materials, project manhours, project contracts, spares etc)

  

Run CJEN first then CNE1 and CNE5.


Regards,

Sanjeev