Sep 26, 2012 at 06:19 AM

Schedule lines to be generated after every interval of time

29 Views

Hi Gurus,

I am facing a problem in generation of schedule lines from MRP. My client requirement is schedule lines which are generating from MRP should come in lots and after some interval of time. For the same requirement i entered planned delivery time as 3 days and in maximum lot size as some value say 300 in material master.

When i run MRP for the same, lots were generated as-

28-09-2012 300 qty

28-09-2012 300 qty 28-09-2012 300 qty 28-09-2012 300 qty 28-09-2012 300 qty 28-09-2012 300 qty

But the requirement is

28-09-2012 300 qty 01-10-2012 300 qty 04-10-2012 300 qty 07-10-2012 300 qty 10-10-2012 300 qty 13-10-2012 300 qty

MRP type is PD and lot size is EX-Lot for lot order qty.

Pls Advice

Best Regards

Aditya Jain