Former Member

Automatic Link tasks cProjects with one WBS element PS

Hello ,

I need some help on this topic.

We are setting up cProjects.

These projects have different tasks and these tasks have to be linked a certain WBS element. ( this can be 7 tasks link to 1 WBS element).

This is part of the Accounting Integration.

Can somebody tell me how to set this up ? Are there BAPI's that we can use ?

Thank you

Davy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 24, 2012 at 10:46 AM

    Hi Berghe,

    If I understood your requirement correctly, my points would be...

    You create Project in cProjects with different Tasks. And now you need to have a single WBS element to be created in PS for all the Tasks in cProjects on integration. i.e.for e.g 7 on 1 mapping.

    For this requirement, you can do the Customization..  Following steps give an idea..

    IMG-cProjects-Accounting Int-Make settings in the ERP-Define controlling scenario.

    Here you can select for Automatic or the Manual creation of the PS Project. And in the 4th column-Contolling Level, you can actually select the Hierarchy of the WBS's on the Replication of cProjects objects(Phase, Tasks etc). Here if you maintain the level as 1, then only one WBS element will be created on replication of you entire cProjects Project.

    Rgrds,

    Santhosh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I believe you need to maintain custom solution to meet this requirement. You can maintain mapping table in your custom program for task type and WBS code extension.

      Once we have done this but I am not remembering all the details related to FM, BAPI, etc.

      Regards,

      Pramod

  • avatar image
    Former Member
    Sep 24, 2012 at 01:16 PM

    Hello Pramod ,

    Thank you for your reply.

    Maintaining the mapping table in your custom program for task type and WBS code extension => what does this mean concrete ? Which mapping table of the custom program are you meaning for task type and WBS code extension and is this the solution to link different tasks with the same task type to one WBS element in PS ?

    Thank you again.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      I am referring mapping table as custom table to maintain mapping between task type and WBS extension. WBS code extension means for certain level of WBS, you can have always fixed extension like. e.g Task type A <--> 01.01, Task type B<--> 02.01. So whatever number of task of same task type will get assigned with one WBS.

      Regards,

      Pramod

  • avatar image
    Former Member
    Sep 24, 2012 at 01:50 PM

    Hello Pramod ,

    This custom table is an existing table in SAP or a table that you have created.

    If so what we have to know is BAPI's and FM.

    Thank you

    Davy