Project delivery CNS0, not picking the Project Stock

409 Views

Hi All,
While processing a ETO scenario, with creating delivery from project, system not picking the project stock.
There is a reservation created from project and unrestricted stock present against project after doing GR from production order.

Material reservation is created with Mov Type 281 with any special stock indicator for FERT material type.

Please let know what may be the issue?.