Sep 21, 2012 at 10:04 AM

Logic to calculate Pending Duration after Rescheduling

16 Views

Dear All,

I have planned an activity with work of 100 Hrs, Normal duration = 11 Days.

Now when i confirm the activiyt for day Hour (start 1st Sep and end also on 1st Sep) and reschedule PROCESSING DURATION (in date tab for the activity) reduces to 10 Days.

Now i do another confirmation for one day with start date as 5th Sep and end date as 5th Sep, and reschedule now system updates PROCESSING DURATION to 6 DAYS, where as it should update processing duration to 9 days.

So to calculate processing duration system considers start date of first confirmation and end date of last confirmation, where as if there are no confirmation in between first and last confirmation system should not consiser these days.....??? is it possible??

Warm Regards,

Jatinder