on 09-21-2012 7:38 AM
Hi All,
I am stuck into a weird issue. I have one prompt on Fiscal Period for Variant Z6 (for L1 Ledger which uses July - June, 4 special periods). In ECC configuration is done as below for this Variant:
Month Day Period Year Shift
1 | 31 | 7 | 0 |
2 | 29 | 8 | 0 |
3 | 31 | 9 | 0 |
4 | 30 | 10 | 0 |
5 | 31 | 11 | 0 |
6 | 30 | 12 | 0 |
7 | 31 | 1 | +1 |
8 | 31 | 2 | +1 |
9 | 30 | 3 | +1 |
10 | 31 | 4 | +1 |
11 | 30 | 5 | +1 |
12 | 31 | 6 | +1 |
But in BW, in prompt, below values are coming:
Fiscal Variant Fiscal Period Fiscal Period Posting Period Fiscal Year
Z6 | 001.2011 | JUL 2011 | 1 | 2011 |
Z6 | 002.2011 | AUG 2011 | 2 | 2011 |
Z6 | 003.2011 | SEP 2011 | 3 | 2011 |
Z6 | 004.2011 | OCT 2011 | 4 | 2011 |
Z6 | 005.2011 | NOV 2011 | 5 | 2011 |
Z6 | 006.2011 | DEC 2011 | 6 | 2011 |
Z6 | 007.2011 | JAN 2011 | 7 | 2011 |
Z6 | 008.2011 | FEB 2011 | 8 | 2011 |
Z6 | 009.2011 | MAR 2011 | 9 | 2011 |
Z6 | 010.2011 | APR 2011 | 10 | 2011 |
Z6 | 011.2011 | MAY 2011 | 11 | 2011 |
Z6 | 012.2011 | JUN 2011 | 12 | 2011 |
Z6 | 001.2012 | JUL 2012 | 1 | 2012 |
Z6 | 002.2012 | AUG 2012 | 2 | 2012 |
Z6 | 003.2012 | SEP 2012 | 3 | 2012 |
Z6 | 004.2012 | OCT 2012 | 4 | 2012 |
Z6 | 005.2012 | NOV 2012 | 5 | 2012 |
Z6 | 006.2012 | DEC 2012 | 6 | 2012 |
Z6 | 007.2012 | JAN 2012 | 7 | 2012 |
Z6 | 008.2012 | FEB 2012 | 8 | 2012 |
Z6 | 009.2012 | MAR 2012 | 9 | 2012 |
Z6 | 010.2012 | APR 2012 | 10 | 2012 |
Z6 | 011.2012 | MAY 2012 | 11 | 2012 |
Z6 | 012.2012 | JUN 2012 | 12 | 2012 |
Z6 | 001.2013 | JUL 2013 | 1 | 2013 |
Z6 | 002.2013 | AUG 2013 | 2 | 2013 |
Z6 | 003.2013 | SEP 2013 | 3 | 2013 |
If you see Description for 007.2012 is incorrect. It should be JAN 2013. Year is wrong. So is the case with other FP'S From 007.2012 - 012.2012.
I have reloaded data from ECC by starting "Transfer Global Settings" process, no luck..
Please guide me.
Regards
Amandeep
Hi Sharma,
we can fix this Fiscal year Text by using the general setting in SPRO --> SAP NetWeaver -> Business Intelligence ->Settings for Reporting and Analysis ->Set F4 Help and Hierarchies for Time Characteristics/OLAP Settings and execute . In that general setting and make the changes in the 1 Fiscal Year as in Master data Text for the Time characteristics.
If the setting is 1 Fiscal year, then make the changes to 2 Calender year and try it
Then in the report level u will get the correct text for the Fiscal year Text.
Thanks
Alex
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alex,
Thank you for your response. After making it 2 Cal Year, I am getting below values in prompt:
Fiscal Variant Fiscal Period Fiscal Period Posting Period Fiscal Year
Z6 001.2011 JUL 2010 1 2011
Z6 002.2011 AUG 2010 2 2011
Z6 003.2011 SEP 2010 3 2011
Z6 004.2011 OCT 2010 4 2011
Z6 005.2011 NOV 2010 5 2011
Z6 006.2011 DEC 2010 6 2011
Z6 007.2011 JAN 2011 7 2011
Z6 008.2011 FEB 2011 8 2011
Z6 009.2011 MAR 2011 9 2011
Z6 010.2011 APR 2011 10 2011
Z6 011.2011 MAY 2011 11 2011
Z6 012.2011 JUN 2011 12 2011
Z6 001.2012 JUL 2011 1 2012
Z6 002.2012 AUG 2011 2 2012
Z6 003.2012 SEP 2011 3 2012
Z6 004.2012 OCT 2011 4 2012
Z6 005.2012 NOV 2011 5 2012
Z6 006.2012 DEC 2011 6 2012
Z6 007.2012 JAN 2012 7 2012
Z6 008.2012 FEB 2012 8 2012
Z6 009.2012 MAR 2012 9 2012
Z6 010.2012 APR 2012 10 2012
Z6 011.2012 MAY 2012 11 2012
Z6 012.2012 JUN 2012 12 2012
Z6 001.2013 JUL 2012 1 2013
Z6 002.2013 AUG 2012 2 2013
Z6 003.2013 SEP 2012 3 2013
Is it correct now? I am so confused!!
Regards
amandeep
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.