You can create BOM with those materials whatever you proposed with ERLA.
1. Create 3 materials as A, B and C with corresponding Iten Category groups.
2. Create a BOM in CS01 with those materials.
3. Maintain the item Category Determination and Schedule lines determination.
4. Maintain the Pricing in VK11 before maintain the Pricing Procedure.
5. Maintain the Customer Material Info with ABC related to A,B and C in VD51.
If you have any doubts let me know.
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you Narendra and TW.
I'm gonna test this in sandbox and will probably getback.
Thanks once again for your time and answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The pricing condition record(PR00) of ABC will be created as usual via VK11 and it may or may not be the sum total of A+B+C
Yes, ERLA would be the option to go with. As with this item category group, the pricing is at main item level and NOT at sub item level. Thus pricing at ABC and not at A, B, C level.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.