Dear Experts,

I'm creating OTRs in TM 8.1 using the IntracompanyTransportationRequestRequest_In enterprise service and they are 'Completed' and 'Consumed Completely' soon as they are created! Any ideas?

Regards

Steve

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 18, 2012 at 11:47 AM

    Hi Steve,

    in the OTR type you define if requested or confirmed quantities are relevant for planning. If confirmed quantities are relevant for planning and there are no confirmed quantities then the OTR will be completed.

    For instance in case of a purchase order you have always to use an OTR type where requested quantities are relevant because there will be no confirmed quantitites ...
    Regards

    Frank