Hello All,
Scenario - i have created an activity with 80 hrs of work, and Calculation key as 1. Now Based on work center's capacity system calculate normal duration as 10 days (say from 5th April to 15th April; considering all 365 days working for scheduling).
in OPU6 --> I have selected SHIFT ORDER
in CONTROL Parameters for WBS Scheduling --> I have selected SHIFT ORDER
Now i confirm this activity for 1 day and entered the confirmation date as 1st April, and then reschedule the project now system updates the activity with start date as 5th April but end date as 14th April??? I dont want this. is this possible to configure??
Regards,
Jatinder