Skip to Content
0
Former Member
Sep 14, 2012 at 09:01 AM

Rescheduling after partial confirmation of any activity

46 Views

Hello All,

Scenario - i have created an activity with 80 hrs of work, and Calculation key as 1. Now Based on work center's capacity system calculate normal duration as 10 days (say from 5th April to 15th April; considering all 365 days working for scheduling).

in OPU6 --> I have selected SHIFT ORDER

in CONTROL Parameters for WBS Scheduling --> I have selected SHIFT ORDER

Now i confirm this activity for 1 day and entered the confirmation date as 1st April, and then reschedule the project now system updates the activity with start date as 5th April but end date as 14th April??? I dont want this. is this possible to configure??

Regards,

Jatinder