Progess Analysis Overview Reports

1044 Views

We are using the CJ20N transaction, progress tab, in order to update the percentage of completion plan of our project. And we are using CNPAWB - Progress Analysis Workbench transaction to update the actual percentage of completion.

When we perform the transaction CN5E to obtain the Progress Analysis Overview, the system is showing in the report all the POC values in zero; although the values are registered on the table COSR.

Anyone know why the CN5E report is not showing the POC values?