No dates in Evoluation (PPM 5.0)

Former Member
0 Kudos

Hello!

We test following process in PPM 5.0:

  1. A project are loaded from MS Project file
  2. Elements (project def or task) of the  loaded project are linked with WBS (multilevel)
  3. In PPM we control dates, at WBS the are  budget\costs\revenue that we see on dashboard or in evolutions

By testing we have found two problems

  1. 1. For the loaded project DPR_EVE_BATCH_DPO (0_DASHBOARD) shows "Program exception: An exception with the type CX_SY_DYN_CALL_ILLEGAL_". For the handmade project there is no problem and we see dates on dashboard. The project type for both projects is the same.

The difference I see, for example, in table DPR_OBJLINK: for the handmade project OBJECT_KEY = WBS, for the loaded project OBJECT_KEY = GUID+name of .mpp file.

What may be wrong with the loaded project?

2. There are no data in evolution 0_PROJ_COSTS_R3 for both projects. But on the tab «Accounting» we see budget, costs etc.. From what table takes the evolution its data? What program fills this table? DPR_EVE_BATCH_DPO (0_OLR3_COSTS) shows «Extraction was carried out successfully», but I don`t now if it`s right program.

Current customizing

Accepted Solutions (0)

Answers (1)

Answers (1)

gerry_hodgins
Active Participant
0 Kudos

Hello 

have you tried note 1340407?

Ger

Former Member
0 Kudos

Our system is 605. So we can't implement this note.