Transferring forecasts from one plant to another

Former Member
0 Kudos

Hi All,

I have certain forecasts for a particular plant which needs to shut down now. Need to transfer these forecasts to the new plant.

Should i be doing it manually in MD61 or there is better way available for this??

Regards

Neeraj

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can use the COPY option (Refernce F9) button in MD61 to copy the PIR. Also you can use Reremnt Plan to mass upload of PIR for multiple materials.

Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks Rupesh.

Issue being looked into by concerned.

Thanks for the information anyways.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Other way around is BDC or BAPI BAPI_REQUIREMENTS_CREATE  for MD61you can get your current requiremnt from PBED table to upload same for another plant.

All the best.

Regards,

R.Brahmankar