on 09-07-2012 6:19 AM
Hi All,
I have certain forecasts for a particular plant which needs to shut down now. Need to transfer these forecasts to the new plant.
Should i be doing it manually in MD61 or there is better way available for this??
Regards
Neeraj
Dear,
You can use the COPY option (Refernce F9) button in MD61 to copy the PIR. Also you can use Reremnt Plan to mass upload of PIR for multiple materials.
Regards,
R.Brahmankar