Re: Where to enter/update hourly rates in cost center planning.

Former Member
0 Kudos

Dear Sapmates,

I am trying to update hourly rates planned for a cost center, I need some guidance.

How does the process of calculation of hourly rate in cost center planning done. Is it using both KP06 and KP26. If yes, how does system calculate the hourly rate for a cost center? and waht is the difference between the variable and fixed price here?

If i have to update the hourly rate of cost center, do I have to udapte prices in both KP06 and KP26 ??

Any help is much appreciated. Thank you in advance.

Best regards,

Pabbi.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi ,

To do the cost center planning i.e cost center wise plan cost we use kp06,,,,,

KP06 will used to do the activity palnning i.e upadate the activity rate or activity rates for all the productions cost centers.

If you maintain the the activity hours in kp26 then you have to do the cost center planning, and based on requirement either run assessment / distribution for cost allocation .

Then you have to the cost center splitting if you use independent planning..... (KSS4)

after that you have to run the plan activity rate calculation by using KSPI transaction ...

Activity rate = Total Plan cost/ Total Plan activity Hours .

If you maitain Directly Activity rates in KP06 then no need to run the KSS4 and KSPI .