on 09-05-2012 6:14 AM
Dear pp gurus i am sd consultant
i want to 2 things pl check
In MMR MRP 2 View or MRP 3 View we use to maintain RLT but my Doubt is if we maintain in mrp 2 view system will take total of Inhouse production time + GR processing time and will propose end of lead time based on this and gives availability confirmation,irrespective of quantity.
and if we maintain mrp 3 view, date proposed for 50 ( what ever me maintain) would always be end of lead time, irrespective of quantity.
plz give so more clarification on this ...little bit confused here....
and RLT IS MANDATORY FOR availability check bz i read one thread in this RLT IS not mandatory written pl check..http://scn.sap.com/thread/1077318
Hi Lavanya,
As per my knowledge, the main difference between RLT and Inhouse production time is
RLT: The time taken to produce 1 quantity of the header material by considering all the dependent requirements procurement and production lead times
Inhouse production time :The time taken to produce 1 quantity of the header material without considering all the dependent requirements procurement and production lead times
generally the system will consider the RLT to propose the delivery date in sales order, but if the RLT is not given for any FG, the system automatically will consider the Inhouse production time to propose the delivery date.
Regards,
Krishna Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Lavanya,
RLT will be required for any material,if in the scope of check for a checking group and checking rule if
the check box for - Check without RLT is not included.
The following options exist for materials produced in-house if the replenishment lead time is included in the availability check:
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
It depends upon the setting of availability check if you have setup your scope of check OVZ9 to consider the RLT then it is useful.
If you maintain the RLT in MRP3 view system will consider it if you don't maintain it then takes total of Inhouse production time + GR processing time. RLT is not mandatory you can do the availability check without it also. Go to OVZ9 check the field Check with RLT put F1 there you will come to know the significance of it.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Read note: 321803 (entirely)
Section : Scope of check :: Point 2. (particularly)
You will understand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.