Friends,
If my understanding is right Rem Pln Ord Value is the cost which is not been converted into Commitment or Actuals yet and since it is a part of the plan value it adds up to the Assigned value. Further, the breakdown of these value can been seen in Budget reports with respected to the network numbers under respective assigned WBS element.
However, I am seen a cumulative Rem Pln Order value at the WBS element level in S_ALR reports but when you further drill down it does not appear at network level. What can be the reasons for this...?
Regards,
MS