Hello All,

I want to create a WBS with reference to another WBS within the same project along with the corresponding activities.

I am able to do this by right clicking on the WBS and selecting include WBS,... --> this creates the new WBS and the crrespondign activties but system also creates a new NWP for this WBS & activities... is there any way to create these new WBS/Activities with the activity assignment to the NWP of the reference WBS??

Warm Regards,