cancel
Showing results for 
Search instead for 
Did you mean: 

Do not see complete cost estimate in the Production order

Former Member
0 Kudos

Hi,

I have done a standard cost estimate (CK11N). But now on the Production order, I do see some of the information pulling in from the estimate, but the Activity Type input is missing.

Please help

Thank you

Accepted Solutions (1)

Accepted Solutions (1)

madhusoodanan_ramachandra
Active Contributor
0 Kudos

Hi Jan,

Please check the following points...

1) Have you maintained activity prices have been maintained in cost centers as planned prices ?

2) Have the cost centers mentioned above are linked to work centers ?

Best Regards,

Madhu

Former Member
0 Kudos

Madhu,

Thanks for the reply,

I have done all of the above,

I have a complete standard cost estimate with the activity costs, I just do not see the complete estimate on the order.

Thanks

Answers (0)