on 08-27-2012 8:41 AM
Hi,
How to map Measurement System Analysis (MSA) in SAP QM module.Please explain the process flow and configuration required.
Regards,
Pragalathan.S
Hi,
Basically its an Qm-PM integration, where u need to assign the 14 inspection type against PM order type for ur equipments and then creation of task list via IE01, then create single cycle or assign strategies for defined frequeny as mentioned in SOP of equipment then create order once u release the PM order then there will be a lot in QC where u need to feed the result or measurements, very important thing is to assign the inspection point 300/310 for FL and Equipment in there task list.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.