Skip to Content
0
Former Member
Aug 27, 2012 at 06:25 AM

Consumption of PRT Material

45 Views

Hello Everyone

I never worked on PRT scenario .so please guide me how to maintain in routing ? how to consider the consumption of prt in routing ?

My scenario is MTO . So i created 1 PRT say as drilling tool this tool is maintained in routing with base qty 1. but this tool may be used more than 4 order .so how we maintained consumption. so cost of that tool also added in costing

Please explained with example . my concept is not cleared regarding PRT

Regards

Sushant