Hi All,

in getting revenue for respective WBS element i am doing PS SD integration. During this process DIP profile plays a major role. I am not able to open DP81 trans code whenever i am trying i am getting the error which is attached. could anybody help me out as i don't have SD consultant .

Thanks,

abhinay

DIP error.png (136.8 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Aug 27, 2012 at 06:18 AM

    The error is self explanatory.

    Check your DIP Profile configuration. Especially the material determination part.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Gokul,

      actual i started project with activities ie. internal activity confirmation gives us actual cost which is the source in DIP configuration. based on this revenue will be billed. but my superior wants project without activities. Is that possible, if so how can we get actual cost and how it is useful in getting revenue?

      2) in activity confirmation process after getting actual cost . how exactly revenue is billed? upto my knowledge in saled order we planned revenue and in billing plan the milestone dates are given as billing dates. once ativity are confirmed based on milestone dates revenue is triggerd. If so how exsactly revenue is billed?

      please help me out.

      thanks,

      abhinay.

  • avatar image
    Former Member
    Aug 27, 2012 at 08:46 AM

    Mr Tushar,

    thanks for your confirmation, i too inform my team leader in the same ,but he wants me to do the project with less configuration as they want to use it internally in the company the people who going to use don't have knowledge regarding SAP. Anyway thanks for your confirmation.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      You can still create revenue project with only WBS elements.

      But you miss out lot of features that Network activities bring in to the project.