hw do i convert planned order from snp to ppds ? wht is the tcode and wht other steps do i need to follow...?? any idea
Rahul,
You are ignoring the rules of engagement for these forums. http://scn.sap.com/docs/DOC-19331
Rule number one on this list is that you should first search for an appropriate answer before posting your question.
This particular question has been asked and answered multiple times. Continuing to ignore rules of engagement will draw unpleasant results from the moderators.....
SAP help:
http://help.sap.com/saphelp_scm70/helpdata/EN/c5/c4703736bfb37de10000009b38f8cf/frameset.htm
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There are several ways:
1). In product view (/n/sapapo/rrp3), you can select the SNP planned order and convert it by
2). You can also run product heuristic in product view, then SNP planned orders in PPDS horizon will be deleted and PPDS heuristic will create PPDS order to cover the demands in PPDS horizon.
3). Run program /SAPAPO/RRP_SNP2PPDS. You can select proucts and input conversion heuristic to do the conversion.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.