Line Item Reports / Planned costs

Hi,

I've configured WBS structure so the user can plan costs for work on a network level, this network its always attached to a WBS element which act as a cost collector for the project.

Now, i understand from the manual, that networks do not create line items, but i was expecting planed costs to be shown on the transaction CJI4 on a WBS element level. Since the WBS element usually collects all the costs from the network below.

This planned costs aren't shown when i run the line items report.

Is there any way I can make this happen?

If i cant the only thing I can think of its to plan directly on the WBS element but since this process is mostly manual it might end up being to slow for the user.

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Aug 25, 2012 at 02:52 AM

    Hi,

    Maybe i  can give you some advice.

    Fist you should assign a user status to WBS, which the business transaction "plan line items" is assigned.

    Then you can use CJ40, there is a check button when you go into the plans by Cost Element. It should distribute your plans and post the line items.

    Hope it can works.

    Regards.

    Ocean.