Transfer from project stock to unrestricted?

Hi gurus,

Could you help me, is there any standard MvT which can transfer material quantity from project stock from one plant to unrestricted stock of another plant? How to manage this requirement?

Thanks,

Anna

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 24, 2012 at 08:25 AM

    Hi,

    Have you tried with Mvt Type 309+Q?

    /Manoj

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 24, 2012 at 10:29 AM

    Hi,

    Use Movement type 301+Q. Ones you transfer material plant to plant use movement type 411+Q.

    Regards,

    Ashish Panchal

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.