Hi,

we've have a strange behavior that I haven't discovered before:

When a completion deadline exceeds, the task gets suspended (with lifecycle status canceled) and a new task is created.

As far as I know this wasn't the case before, the task always remained with status 'Ready'.

What can be the reason for that?

In BPM the affected task raises a critical exception.

Does that have the effect that the task gets suspended?

Thanks in advance,

Eddie.

SuspendedTask.jpg (93.0 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 31, 2012 at 11:55 AM

    Hi Eddie,

    the important information is that the task has been canceled. This is a final state regardless if it is suspended or not. However, the behaviour is according to the documenation:

    http://help.sap.com/saphelp_nw73/helpdata/en/54/bf98c82cd84614a85cfda25d70b175/frameset.htm

    You should check if non-critical exceptions are doing the job in your case.

    Best regards.Stefan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.