Does MRP job fail if physical count is occurring

Hi,

I have a question to PP gurus.

Does MRP run job fail if physical count is occurring.

Please let me know relation between MRP run and physical counting like what steps we take while we do physical counting anfd MRP run.

Regards


Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Aug 21, 2012 at 05:13 AM

    Dear,

    What do you mean by physical count is occurring? Could you please elaborate it?

    Do you mean physical inventory then there is no direct relation with MRP.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.