Forecast Based planning

Hi,

I am performing forecast based planning for a material. I run the forecast and then transfer them to demand mgmt. My forecast requirement for the 1st month is 55 and 2nd month is 55 and 3rd month is 55 . I have a available stock of 50. So according to the forecast based planning it should generate 3 purchase requistion of 5 qty for 1st month,55 qty for 2nd month, 55 for 3rd month but it is generating 5,55,110,110 what is the reason .please find below the screenshots

pastedImage_0.png (68.6 kB)
pastedImage_1.png (64.7 kB)
Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 18, 2012 at 12:06 PM

    Badari,

    If you copy the forecast requirements to Demand Management, then you must deactivate the forecast afterward.

    Most people who use forecast based planning do not transfer to DM.

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

    • hi,

      It means that if we transfer forecast requirement to demand management does the system treats forecast requirement as seperate and requirement in demand management as independent requirement so is this the reason it it generating 4 purchase requistions.

      Regards

      Badri

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.