How to execute the function 'calculate periods' by background job to refresh the Planning Calendar?

Hi Experts,

We use Factory Calendar assigned in APO Planning Calendar (Time Stream).

When there's update in Factory Calendar from R3 to APO, in order to update the buckets in the APO planning calendar accordingly, how to refresh the APO planning calendar?

Your input is appreciated,

Thanks

Mandy

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 15, 2012 at 09:37 AM

    Mandy,

    Refer to note https://service.sap.com/sap/support/notes/1245264 The report is /SAPAPO/TIMESTREAM_UPDATE.

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Ezekiel,

      Yes, this is an old thread. I normally don't answer 'tack-on questions', but this one is easy.

      First, I never mentioned anything about 1234264.

      The note I did cite (1245264) still appears to be valid 'up until now' - but, like all notes, only for the Releases specified in the note.

      Best Regards,

      DB49

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.