I want to automate the creation of audit in PLMD_AUDIT, once the quality notification is released, Is there is any way to link notification and audit, please advice..

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor

Dear,

Please try the Badi PLM_AUDIT_ACT_LINK, method CREATE_OBJECT. and business object BUS2078 ('quality notification').

Regards,

R.Brahmankar

former_member512784
Participant
0 Kudos

Hi Rupesh

Thanks for your reply.

I think the badi you mentioned is used to trigger notification from audit, but my requirement is to trigger audit from notification.

But I'm not sure, please correct me, if can I meet the requirement with the same badi.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

I am not sure about it but you can explore the option given under the BADi like CREATE_OBJECT_AT_RELEASE else you can use the workflow for same.

All the best.

Regards,

R.Brahmankar

former_member184536
Active Contributor
0 Kudos

Dear E.M

As per the business process Audit is done to know how the process is going on and it is as per the SOP or not. And if it is not as per the SOP then NC(major, minor ) given by Auditor.

So if while doing Audit, and NC is generated then we can create Notification for that concering the dept. users. So Notification is generated from Audit.

Audit is not done when defect are produced or notificatonis generated. It is standard Business Process.