Hi all
We are observing the delay start in most of our batch jobs in all env, i have changed the rdisp/btctime from 60 to 30 sec and incresed the BTC A jobs from 1 to 3..
still no result.... there are more than 50 BTC processors in the system and most of them are in waiting state...
Is there any other analysis i can check to why the delay in starting the job by SAP.
Thanks,
Subhash.G
Hello,
Check SAP note 923228.
Regards,
David
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
How are the batch jobs scheduled in your SAP landscape ? Do you use any third party scheduling tool ?
Regards,
Samik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Subash,
Check SAP Note 1057255 - Jobs remain in status 'ready'
Thanks,
Sreeni
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.