Former Member
Aug 10, 2012 at 08:33 AM

Production order labor activity cost

385 Views

Hi,

I have maintained labor price for 1 hours as 200$ (fixed price 100$ and variable price as 100$) in KP26.

However after production confirmation, for actual posting of 1 hour, the cost is coming as 201.14$ (Fixed=100.57$ and Variable=100.57$).

Please clarify why extra 0.57 is coming.

Regards,

Santhosh