KKA0-WIP cut off period - for different company codes

Former Member
0 Kudos

Hi,

We have a multiple company codes. the transaction KKA0(zero) -WIP cut off Period , is for the entire comtrolling area.  We wanted to setup as background job so it would run at certain date and time for entire controlling area. But the Program for kka0 doesnot allow for that.

Is there anyway we can separate this by various company codes? as one company's controller doesnot to run for entire controlling area and just his own.

Can others who have similar scenario let me know how you are handling this?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi  Manisha,

This setting is at controlling area/Version level. So this cant be done at company code lever unless you have 1:1 controlling area and Company code assignment

I doubt we have any background program for KKA0 that facilitates background scheduling.

Regards,

RK