Presently our system IMRO process is doing without QC release, now we decised to change the process as like (MIGO -> Insp lot -> release -> MIRO),
that's block the IV before QC release.
Please help me how to now configure this process. please explain step by step.
Regards
Surya
HI Surya,
This topic is dealt in clear steps in the following document:
Please go through the same to configure the requirement.
/Manoj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Surya,
It is not possible to block the posting of invoices through MIRO or MIR7 before Quality release but only possible to prevent the payment to FI.
As a workaaround, you can only prevent automatic posting of invoice for a material by using the QM procurement key in the material and using GR-Based IV. This would prevent the invoices to be done until the more than 1 GR is is posted and an inspection is carried out for each GR.
Hope, my reply helps. However, there are several threads existing in SDN. You may refer to one like:
http://scn.sap.com/thread/1872310
Regards,
Agreta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In standard you can only block payment, it does not block invoice entry.
If you want block invoice entry, then you have to control this in a user exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.