Hi all,

I have a scenario where we are sending the subcontracing components through third party vendor and not from the their own facility.

For the finished product the PR is creating from MRP, but i also want the components for the finished products to be run through MRP, so the PR are created automatcially.

I came through SAP help that through MRP area it is possible. Without creating MRP area whether it is possible to run MRP for components.

Your input would be helpful a lot.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)