Dear Sir,

Our plant say 1101 consist of Two storage location 2001 and 2200. 2001 is for shop floor production while 2200 is for warehouse.

So 2001 location ask for components (materials) for packing from 2200 location by creating requisition through mb21, while 2200 location refer this requisition number and give the component to 2001 location.

Now what i want to understand is that, how MRP can automatically ask for requisition to 2200 location for shop floor peoples.

What would be the right process.