Aug 07, 2012 at 09:59 AM

Problem with strategy 11 - Gross Requirements Planning

165 Views

Hi Gurus,

I implemented the strategy 11 for MTS production. For this test i have created 2 PIRs (BSF type) and i ran the MRP. The system created 2 planned orders, it didn't take the stock into account nor the sales orders (so far so good).

I then converted one of the planned orders into a production order, released it, made the components consumption and the goods receipt for the finished product.

The thing is, after the produced quantity of the finished product enters the storage stock, the PIR wasn't reduced, it just stayed there. With a new MRP run, the system created a new planned order for that same PIR.

Shouldn't the PIR be reduced during the goods receipt stage of the finished product? If so, what am I doing wrong?

Thanks in advance,

Kind regards,