Planned Independent requirement quantity

Dear All,

For a particular material and plant, i would like to get the planned Indipendanat requirement for some weeks time and then display the total quantity in a report.

For example when the report is executed today..i should get the total Independent requirement quantity for next 5 weeks.

From which tables i can fetch this info..or is there any FM available for this

Regards

Shyam

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Aug 06, 2012 at 03:42 PM

    Hi Shyam,

    SAP Query with table joins of tables- PBIM, PBED, PBHI should satisfy your requirement.

    Check & revert.

    Regards,

    Anup

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 06, 2012 at 07:15 PM

    Hello

    You can use BAPI_REQUIREMENTS_GETDETAIL to read the PIRs on a custom program, but I believe that this information is already available on transaction MD73.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.