Hi,

I have got a requirement where I have to disable or deactivate Budget Billing of a Contract.

How I enabled Budget Billing of a Contract after Move-In ?

--> I am taking care of the scenario where I have enabled the Budget Billing service after Move-In of the Contract.

Firstly, I updated the data at Contract Account level where the field BB Procedure is updated to Budget Billing Plan Procedure. After this, I updated the TEPYPM table using ISU_DB_TEPYPM_UPDATE function module which corresponds to EK95 T-code where we maintain Manual History of the Contract. The data stored is starting from 12 months prior to Move-In date till Move-In date.

I am also asking the user to provide Budget Billing amount which is updated in the TEPYPM table. After updating the table, I have changed the Contract data, where I have provided Payment Plan Type as Budget Billing Plan, Starting Month, Alternate Starting Month and Joint Invoicing as 3 that is the Contract must not be invoiced with other Contracts.

Please let me know if I have missed any step from above.

Now, I need to disable or deactivate Budget Billing from the Contract.

Please let me know the total procedure involved in deactivating the BB from the Contract.

Thanks,

Manish Verma

1 ACCEPTED SOLUTION

Former Member
0 Kudos
4 REPLIES 4

Former Member
0 Kudos

Hello Manish,

Please check this link.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/27/6a7cf41fc811d6b1d500508b6b8b11/content.htm

Hope this helps you out.

Regards

Sachin

0 Kudos

Hi Sachin,

Thanks for the info but the link does not say about the T-codes or changes required at SAP end in order to deactivate the BB Plan.

I want to know the FMs or BAPIs or T-codes involved to make desired changes.

Regards,

Manish Verma

0 Kudos

you should be able to use BAPI_ISUCONTRCT_CHANGEFROMDATA and clear the value in PYPLS (start month) so that contract will be removed from payment plan.

0 Kudos

Thanks William.

Removing Start month from the Contract level disables the Budget Billing.