Hi Experts,

We are using Scheduling agreement for procurment of RM from multiple vendors.max lot size is discuss with vendors and maintain in Quota arrangement (MEQ1),Quota usage(4) is define in purchasing view of Material Master or RM.

after MRP run system is showing Purchase requisitions for three vendors.

But we want to have Schedule lines insted of Purchase requisitions in MD04 after MRP run.