Hello sir,

I had some doubt in release strategy. I had make Po of rs.100 and it was already released. Now I try to do ahmedment in that and do net price of rs. 80 instead of rs. 100, at that time system did not ask for release(in that case system will not ask for it). But, if I will do with rs.90 instead of rs. 80 at that time, auditor wants to go that PO for release approval.

Is it possible then How?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Aug 02, 2012 at 09:34 PM

    Hello,

    Once you release the PO with value, e.g 100, system will insert this value on field EKKO-RLWRT.

    When you change the PO, system will compaire if the value (after change) is HIGHER than the value stored on EKKO-RLWRT, and in case it is, it will reset the release (in case you have release indicator 4 or 6).

    Thank you & Regards,

    Eduardo

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 02, 2012 at 11:10 PM

    Hi

    According to SAP Note 493900 reset of the release strategy for purchase order only takes place if CEKKO-GNETW is higher than the old one or CEKKO-GNETW fall off a lower interval if there is no tolerance limit maintained.

    Regards

    Viru

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 02, 2012 at 07:44 PM

    how is your release indicator customized? what changability have you set and what percentage of change?

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 03, 2012 at 01:49 AM

    Hi,

    What I understand per business demand , you want design your release strategy where release will triggers again, if any value changes( increases or decreases) in the purchase order.

    Yes, you can do it after configuring release strategy with different levels but for your special requirement, you need use User exit:EXIT_SAPLEBND_002 which will be playing vital role {In design to act for PO release and re-triggers release again within same release strategy, discuss with ABAPer to design for codes}.If PO value increase 1 or any value within same release strategy,then PO release to re-triggers again and if PO value decrease 1 or any value within same release strategy,then PO release to re-triggers again!

    NOTE:

    Yes of course you can use changeability indicator 6 in designing of release indicator for purchase order release but that will helps to RE-TRIGGERS release again if PO value changes or value exceed to next level but not within same release strategy.

    Refer my answer to a similar type of thread where requirement is little thin line differs😊

    http://scn.sap.com/thread/3216685

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.