on 07-31-2012 2:52 PM
Hello Friends
I have created a purchase order for one new material on one vendor for a plant say material code ABC, vendor code PQR for plant XYZ. Prior to purchase order creation, I have not created any purchase info record. The info record created automatically. When I am displaying the purchase info records by using the transaction ME13, in Purchase Organization Data1, the "Valid to" date as showing as 31.12.9999. Where as in purchase order the validity end date has given 31.12.2012 only.
Could you please explain in purchase info record why it is showing 31.12.9999 from where system is bringing this date?
Best Regards
Vijayakumar TVN
Hi,
This is standard functionality where the system creates a Purchase Info Record from the Purchase Order when the Info Update indicator is set in the Material Data Tab.
Now these all happens:
So each time you create a PO, these details will be fetched from the PIR and the price if not maintained manually in ME12 will be fetched from the last PO.
/Manoj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Manoj
Thanks for your immediate feedback and this is helpful answer
Could you please clarify the following points?
1) In PO, if I have not selected Info Update indicator in Material Data Tab, what is the status?
2) As you said Price in PIR is empty, In PO already price is available but why price is not appearing?
3) The validity period is 31.12.9999 but in by using ME12 transaction the field is in display mode only
Best Regards
Vijayakumar TVN
Hi,
1. If Info Update Indicator is not set in the PO, then the system will not create a Purchase Info Record this material.
2. That is the functionality of the PIR, only from Quotation/Outline Agreements it is defined to copy the prices into the PIR. From PO it is not copied into the PIR. The main reason for this is, in SAP for Purchasing Conditions, the PO is only document which is Time Independent all other documents like PIR, Quotation, Outline Agreements are all Time Dependent. Since there are no time dependent conditions in the PO, the system works this way.
3. Yes, again its a standard functionality. You can change the time period by choosing the Conditions tab in the PIR.
/Manoj
the validity to date in the PO is about the validity of the frame work PO.
the validity in the info record is about price condition
the date 31.12.9999 is taken from customizing of condition type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Mr. Jürgen
Thanks for information
Could you please explain the following points
Could you please clarify the following points?
1) In PO, if I have not selected Info Update indicator in Material Data Tab, what is the status?
2) As you said Price in PIR is empty, In PO already price is available but why price is not appearing?
3) The validity period is 31.12.9999 but in by using ME12 transaction the field is in display mode only
4) the date 31.12.9999 is taken from customizing of condition type - Can you please explain what is the purpose of giving condition type. Here in Inforecord, price is the main factor.
Best Regards
Vijayakumar TVN
hi,
Have you seen help text...
Date until which the price shown in the info record is valid.
If there is no price that is valid on the current date, the last-valid price is displayed and the date field contains the day before the start of the next validity period (this may be 12.31.9999 if there is no further validity date). If all validity periods lie beyond the current date, the price of the next period is displayed. The date field then contains the end date of this period
Regards,
PK.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vijayakumar,
This is standard system behavior.
If purchasing info record is created automatically then system sets the 'valid to' date as 31.12.9999. Later you can change this date as per the requirement. The valid to date from info record doesn't depends upon the PO validity end date because info record 'valid to' date is for the condition type. If info record is created manually then during creation you can set the 'valid to' date as required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello shailesh kurdukar
Thanks for your immediate feedback and this is helpful answer
Could you please clarify the following points?
1) In PO, if I have not selected Info Update indicator in Material Data Tab, what is the status?
2) As you said Price in PIR is empty, In PO already price is available but why price is not appearing?
3) The validity period is 31.12.9999 but in by using ME12 transaction the field is in display mode only
Best Regards
Vijayakumar TVN
Hi Vijaykumar,
1) System will not create info record in the background, when PO is created for new, vendor and material combination. You can check this in your test system.
2) This is standard behavior of system. In this case, system copies price from last PO for the material and vendor combination.
3) Click on the 'Conditions' tab, then you will find the 'Valid to' field in the editable mode.